๐Ÿ“ What is it?

Conduit rough-in benchmarks help field teams measure realistic daily output during above-ground electrical installations โ€” especially with EMT and MC. These metrics support planning, crew allocation, and schedule forecasting.

๐Ÿ”น Daily Output Benchmarks (Per Installer)

EMT Rough-In

  • 1/2" EMT: 310'โ€“410'

  • 3/4" EMT: 270'โ€“370'

  • 1" EMT: 230'โ€“300'

MC Cable Pull

  • Small (#14โ€“#8): 400'โ€“500'

  • Large (#1/0โ€“#250): 175'โ€“250'

Flex Conduit

  • 1/2" Flex: 350'โ€“500'

  • 3/4" Flex: 300'โ€“450'

โœ… Why it matters:

These benchmarks give you a realistic target for crew output โ€” not pie-in-the-sky estimates.

They help catch productivity slumps early and justify manpower increases or delays.

You can compare actuals vs. expected to coach the team or improve routing/layout efficiency.

๐Ÿ› ๏ธ Pro Tip:

Log conduit install per route type: overhead rack, tight ceilings, in-wall, or exposed. Use color-coded plans to visualize progress vs. target.

๐Ÿ“Š Interpreting the Data

  • ๐Ÿ”บ Above target? โ†’ Lean crew. Great for tight timelines.

  • โš–๏ธ On target? โ†’ You're tracking just right.

  • ๐Ÿ”ป Below target? โ†’ Check for issues: material delays, layout changes, congested areas.

๐Ÿงพ Simple Example

๐Ÿ”ง Task: 3/4" EMT Rough-In

  • Daily Goal: 350 ft

  • Actual Output: 290 ft

  • % Achieved: 83%

๐Ÿ”ง Task: 1/2" Flex Conduit

  • Daily Goal: 400 ft

  • Actual Output: 420 ft

  • % Achieved: 105%

๐Ÿ”ง Task: Large MC Pull

  • Daily Goal: 225 ft

  • Actual Output: 180 ft

  • % Achieved: 80%